Construction Projects
Click the link below to view an interactive map of this year's construction projects. In the map you can select a project to read more details about the project.
Interactive Construction Map
| Project | Project Location | Project Type | Start Date | Completion Date | Contractor | Project Cost |
|---|---|---|---|---|---|---|
| CSAH 3 | US Highway 218 to CSAH 7 | Cold-In-Place Recycling & Bituminous Overlay | June 2026 | September 2026 | Ulland Brothers, Inc | $3,854342 |
| CSAH 15 | CSAH 10 to CSAH 8 | Cold-In-Place Recycling & Bituminous Overlay | June 2026 | September 2026 | Ulland Brothers, Inc | $1,423,689 |
| CSAH 16 | CSAH 2 to CR 57 | Full Depth Reclamation & Bituminous Overlay | June 2026 | September 2026 | Ulland Brothers, Inc | $724,966 |
| CR 57 | CSAH 16 to CSAH 20 | Full Depth Reclamation, Cold-In-Place Recycling & Bituminous Overlay |
June 2026 | September 2026 | Ulland Brothers, Inc | $1,789,723 |
| Bridge 50604 |
CSAH 7 | Bridge Replacement | January 2026 | June 2026 | ICON Constructors, LLC | $996,655 |
| Bridge 50605 | CSAH 7 | Bridge Replacement | January 2026 | June 2026 | ICON Constructors, LLC | $1,046,073 |
| Bridge 89212 |
CSAH 5 | Bridge Replacement | TBD | TBD | TBD | $425,000 |
| Bridge L8597 | 505th Avenue Lyle Township |
Bridge Replacement | TBD | TBD | TBD | $600,000 |
| Bridge L4980 | 210th Street Marshall Township |
Bridge Replacement | July 2026 | September 2026 | Alcon Excavating | $209,634 |
| Bridge L5013 | 115th Street Lyle Township |
Bridge Replacement | July 2026 | September 2026 | Alcon Excavating | $410,840 |
| Bridge 50J03 | 720th Avenue Pleasant Valley Township |
Bridge Replacement | July 2026 | September 2026 | Midwest Contracting | $131,274 |
CSAH 7 Bridges Replacement Project SP 050-607-043
This project includes the replacement of two bridges on CSAH 7 between CSAH 1 and CSAH 2.
Grant: MnDOT Agreement No. 1061602/ SP 050-607-043/ Minn. Project No STBG 5026(103), Local Bridge Replacement Program
Agency Leadership: Mitch Wenum PE, County Engineer, 507-437-7718 MitchW@co.mower.mn.us
Grant Manager: Sarah Covert, Highway Accountant, 507-437-7718, SarahB@co.mower.mn.us
Contractor: ICON Constructors, LLC of Mabel, MN